The completion rate of cardiovascular hospital thus far

The cadres of the Strategic Projects Department at the Holy Shrine continue their work on Khatam al-Anbiyaa' hospital project for cardiovascular diseases in Karbala.
 
 
Maitham Shaker Yasser, the engineer supervising the project, said in a statement to our centre, “The Khatam al-Anbia Hospital project for cardiovascular diseases has a room for 100 beds and expanded to be 157, as the current completion rate is 63%, with high efforts ongoing work."
 
 
He added, "The mechanical works represented in the water and sewage pipes, the fire system, the cooling piping system, the medical gases system, in addition to the heating system, air ducts, and electrical wires... all of which have reached very advanced levels and been tested in order to find any leaks and check the accuracy of work, noting that all the construction and architectural works are witnessing advanced stages of work as well."
 
 
Ameer al-Moussawy